Beam Commissioning of BEPCII Injector Linac
- Received Date: 2005-10-18
- Accepted Date: 2005-11-10
- Available Online: 2006-06-05
Abstract: This paper describes the beam commissioning process of BEPCⅡ Injector Linac. Aiming at the beam design goal and the beam physics characteristics of this injector linac, the beam commissioning method has been proposed, and some problems met in the beam commissioning process have been analyzed and studied. In addition, the preliminary beam commissioning results have been obtained.





Abstract
HTML
Reference
Related
PDF












DownLoad: